Completed BWDB Structures: up to June, 2020
SL |
Description of Structures |
Quantity |
Unit |
01. |
Completed Projects |
877 |
Nos |
02. |
Total Embankment |
16353 |
km |
03. |
Coastal Embankment |
5788 |
km |
04. |
Submergible Embankment |
2625 |
km |
05. |
Other Embankment |
7940 |
km |
06. |
Irrigation Canal |
5355 |
km |
07. |
Drainage Channel |
4502 |
km |
08. |
Hydraulics Structures |
15488 |
Nos |
09. |
Barrage |
4 |
Nos |
10. |
Rubber Dam |
5 |
Nos |
11. |
Coastal Polder |
139 |
Nos |
12. |
Bridge and Culvert |
5737 |
Nos |
13. |
Road (Including Semi pacca) |
1084 |
km |
14. |
Bank Protection |
1287 |
km |
15. |
City Protection |
31 |
Nos |
16. |
Spur/Groyene |
251 |
Nos |
17. |
River Dredging |
823 |
km |
18. |
River Re-Excavation |
1320 |
km |
19. |
Land Reclamation |
1045.80 |
sq-km |
20. |
FCD Area |
6.496 |
m-ha |
21. |
Irrigation Area |
1.635 |
m-ha |
Note:
** 54 Gauge Station at 29 Rivers.
** With all these interventions 85 million People and 15 million Households are protected from average floods and salinity.
****BWDB contributes 1.60% to the National GDP ****